Current update
Earthworks for the approaches to the new flyover bridge over Lanyon Drive are nearing their final height. Foundation work including underground concrete piling and pile caps – which will support the weight for the bridge over Lanyon Drive – is well underway and progressing smoothly. Pavement construction in the median strip next to both the southbound and northbound carriageways has commenced as part of the highway widening.
Reduced speed limits will be in place for the duration of the work. This will generally be 60 km/h on both highway carriageways while work is underway. Temporary lane closures and speed reductions to 40 km/h will intermittently be in place outside peak periods.
The changed speed limit is required for several reasons including each of the below:
- The project site is a very restricted work area due to the existing carriageway and available median and verge areas. This means works will be carried out in close proximity to the existing roadway and road users.
- Temporary concrete safety barriers adjacent to travel lanes, reduced lane and shoulder widths, and temporary traffic diversions are required to accommodate the works safely.
Construction start: Utility works began on site in January 2022. The main construction works on the Lanyon Drive interchange started in January 2024.
Expected construction completion: End 2026.